10/28/2024, 12:17In anticipation of the autumn-winter period 2024/25 Bishkek Electricity Networks Enterprise, the OJSC ‘NESK’ branch, has completed 95% of repair work on its high-voltage lines. Brigades overhauled 41 kilometres of 35/110/220 kV overhead lines and performed current repairs on 529 kilometres of the planned 552 kilometres.
Also, 3,543 insulators were replaced, 8 defects detected by thermal imaging inspection were corrected and 1,950 trees under power lines were pruned.
To improve infrastructure, angles weighing over 1,145kg were additionally welded.