07/16/2025, 13:13In the city of Jalal-Abad, construction of a new modern polyclinic No. 1, which meets all the necessary requirements, is nearing completion. The project began in 2022 with funding from the republican budget, and the tender price was 156 million som.
Construction work is being carried out under the strict supervision of the Department of Housing and Civil Construction. The total area of the three-storey polyclinic is 3,141 square metres.
To date, the construction of the facility is 87% complete. The polyclinic is scheduled to be commissioned by the end of 2025.