05/15/2025, 13:17The mayor of the capital familiarised himself with the progress of the reconstruction of the DEPO-1 enterprise on Moskovskaya Street and DEPO-2 on Shabdana Baatyr Street. Currently, reconstruction work is underway to accommodate new electric buses and equip them with modern electric charging equipment.
To date, half of the repair work has been completed: closed protective structures have been installed at DEPO-1 and the second layer of asphalt has been laid.
At DEPO-2, this work has been fully completed. Work is currently underway to install electrical equipment and deploy special charging stations.
Construction work at DEPO-2 is scheduled to be completed by 25 May 2025.