06/30/2025, 09:17Construction of pumping station No. 3, located at the intersection of Chui Avenue and Osmonkul Street, continues in the city of Bishkek.
To date, a significant amount of construction and installation work has been completed. The building shell has been completed, bank reinforcement work has been carried out on the western bank of the Alamedin River, power cables have been laid from the Bishkek substation, and the removal of engineering communications, including sewerage, water supply and electrical cables, has been completed.
Work is currently continuing on the installation of electrical equipment, the laying of 1,000-millimetre diameter heating pipes, and the installation of pumping equipment.
All necessary construction materials have already been delivered. The work is scheduled to be fully completed by the end of August this year.