    The Ministry of Construction reported violations during the reconstruction of T. Moldo Street in the city of Balykchy. The contractor, Chu Proxy LLC, laid asphalt that was thinner than specified in the project and did not coordinate the work with a repeat expert review.

    Following an unscheduled inspection, the contractor was issued an order and an administrative fine. However, the company has not yet provided updated documentation. The issue of transferring the case materials to law enforcement agencies is being considered.

    To complete the reconstruction of the street, the Balykchy mayor's office has signed a new contract with 4Enerji LLC.