    In Talas, overhaul of over 217 kilometers of overhead lines will be carried out

    Talas Electric Grids Enterprise will begin overhaul of overhead lines with a length of over 217 kilometers in March.

    As part of the overhaul, work will be carried out in the city of Talas - 4 kilometers of overhead lines, in the Talas district - more than 142 kilometers of overhead lines, in the Aitmatovsky district - 52.5 kilometers of overhead lines, in the Bakai-Ata district - 18.6 kilometers of overhead lines.

    It is also planned to carry out maintenance of 10-0.4 kV overhead lines with a total length of 3.8 thousand kilometers throughout the Talas region.

    Talas PES plans to carry out repair work from March to November, preparing for the autumn-winter period. These activities are aimed at improving the power supply of the region.