07/11/2025, 13:04At the expense of savings after the repair of the Dyikan-Kyzyl-Zhyldyz section of the North-South alternative highway, asphalt is being laid on local roads. The works are carried out on the sections of Dyikan-Kara-Keche (3 km), Zhumgal-Turgol-Sai (3.4 km), Kyzyl-Tuu-Chon-Dobbo (4.2 km), Kochkor-Aral-Tөө-Ashuu (0.3 km) and the road to Epkin village (1.4 km).
More than 3 km of the total plan of 12.2 km has already been asphalted. The works are proceeding according to the approved schedule, and their completion is planned for 2025.
Reconstruction of the Dyikan-Kyzyl-Zhyldyz section (from 159 to 183 km) of the alternative North-South road was completed in 2022 and put into operation in 2023.
As a result of negotiations between the Ministry of Transport and Communications and the Saudi Development Fund, it was decided to allocate the saved funds for major repairs of local roads near the alternative North-South road.