Published
11/06/2025, 12:40In the Talas region, 3,300 porcelain insulators have been completely replaced with glass ones.
The upper parts of the supports and connecting elements were also inspected and repaired where necessary. The overhead line routes were cleared, and trees and shrubs were trimmed.
In addition, major construction work has been completed on the 110 kV Semetey-Pobeda overhead line. Wires, insulators and coupling fittings have been replaced along a 47.06-kilometre section. Thermographic studies and technical inspections of high-voltage lines have been carried out.