06/29/2026, 12:26A number of major road infrastructure development projects are underway in the Tyup District of the Issyk-Kul Region. According to the approved plan for 2026, a total of 71.7 kilometres of roads are scheduled to be asphalted across the district.
In particular, 10 kilometres of the Taldy-Suu–Aral road are scheduled to be asphalted, and work has already begun.
On the 39-kilometre section of the Tyup–Kegen road, work has begun on laying the second layer of asphalt.
On the Mikhailovka–Nikolaevka–Toktoyan–Sary-Tologoy road, 15.5 kilometres are scheduled to be asphalted, of which 10.5 kilometres of surfacing have already been laid.
On the Tyup–Shaty–Ichke-Suu–Taldy-Suu road, 7.2 kilometres will be repaired.
In addition, on the previously asphalted Karkyra–Turuk–Sary-Jaz road, preparations are underway for the application of road markings and the installation of road signs.