05/22/2025, 10:32The Talas Electrical Network Enterprise, a branch of OJSC ‘NESK’, is implementing a large-scale programme to modernise overhead power lines aimed at improving the reliability and safety of the region's power supply.
As part of this programme, 3,300 porcelain insulators are to be replaced with glass ones. To date, 604 insulators have been successfully replaced.
In addition, work is being carried out to inspect the upper parts of the supports and connecting elements, as well as to clean the power lines, including cutting back trees and shrubs.
In June, it is planned to replace the wire on the 110 kV Semetey-Pobeda line, as well as conduct regular inspections and thermographic studies of high-voltage lines.